Fisia Babcock Environment
Year: 2009
Location: Naples, Italy
Type of plant: MVA Neapel
Installation: Cold commissioning, hot commissioning, commissioning shift management
Location: Naples, Italy
Type of plant: MVA Neapel
Installation: Cold commissioning, hot commissioning, commissioning shift management
Martin GmbH Munich
Year: 2008-2009
Location: Gothenburg, Sweden
Type of plant: MVA Renova Gothenburg
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Gothenburg, Sweden
Type of plant: MVA Renova Gothenburg
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
LAB Group Stuttgart
Year: 2009
Location: Bremen, Germany
Type of plant: SWB Erzeugung Bremen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Bremen, Germany
Type of plant: SWB Erzeugung Bremen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Baumgarte Boiler Systems
Year: 2009
Location: Frankfurt, Germany
Type of plant: AVA Nordweststadt
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Frankfurt, Germany
Type of plant: AVA Nordweststadt
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
von Roll Zürich
Year: 2009
Location: Cleveland, Great Britain
Type of plant: SITA Cleveland
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Cleveland, Great Britain
Type of plant: SITA Cleveland
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Martin GmbH Munich
Year: 2009
Location: Twente-Hengelo, Netherlands
Type of plant: MVA Twence
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Twente-Hengelo, Netherlands
Type of plant: MVA Twence
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
LAB Group Stuttgart
Year: 2009
Location: Rostock, Germany
Type of plant: SBS HKW Rostock
Installation: Loop checks, cold commissioning, hot commissioning, commissioning shift management
Location: Rostock, Germany
Type of plant: SBS HKW Rostock
Installation: Loop checks, cold commissioning, hot commissioning, commissioning shift management
von Roll Zürich
Year: 2008
Location: Bamberg, Germany
Type of plant: MHKW Bamberg
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Bamberg, Germany
Type of plant: MHKW Bamberg
Installation: Loop checks, cold commissioning, hot commissioning and trial operation with commissioning shift management
Fisia Babcock Environment
Year: 2007-2008
Location: Borlänge, Germany
Type of plant: SE MVA Borlänge
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Borlänge, Germany
Type of plant: SE MVA Borlänge
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Fisia Babcock Environment
Year: 2008
Location: Uddevalla, Sweden
Type of plant: MVA Uddevalla
Installation: Loop checks, cold commissioning, hot commissioning, commissioning shift management
Location: Uddevalla, Sweden
Type of plant: MVA Uddevalla
Installation: Loop checks, cold commissioning, hot commissioning, commissioning shift management
LAB Group Stuttgart
Year: 2008
Location: Solingen, Germany
Type of plant: MVA Solingen
Installation: Loop checks, cold commissioning, hot commissioning, commissioning shift management
Location: Solingen, Germany
Type of plant: MVA Solingen
Installation: Loop checks, cold commissioning, hot commissioning, commissioning shift management
AE&E Lentjes Ratingen
Year: 2007-2008
Location: Frankfurt am Main, Germany
Type of plant: AVA Nordweststadt
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Frankfurt am Main, Germany
Type of plant: AVA Nordweststadt
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Caliqua
Year: 2007
Location: Horgen, Switzerland
Type of plant: KVA Horgen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Horgen, Switzerland
Type of plant: KVA Horgen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
LAB Group Stuttgart
Year: 2007
Location: Kassel, Germany
Type of plant: MHKW Kassel
Installation: Commissioning management, loop checks, cold commissioning, hot commissioning, commissioning shift management
Location: Kassel, Germany
Type of plant: MHKW Kassel
Installation: Commissioning management, loop checks, cold commissioning, hot commissioning, commissioning shift management
LAB Group Stuttgart
Year: 2005-2007
Location: Mainz, Germany
Type of plant: MHKW Mainz
Installation: Construction management, loop checks, cold commissioning, hot commissioning, commissioning shift management
Location: Mainz, Germany
Type of plant: MHKW Mainz
Installation: Construction management, loop checks, cold commissioning, hot commissioning, commissioning shift management
AE&E Inova Cologne
Year: 2007
Location: Stuttgart, Germany
Type of plant: EnBW Power station Münster
Installation: Remaining assembly
Location: Stuttgart, Germany
Type of plant: EnBW Power station Münster
Installation: Remaining assembly
EVI Abfallverwertung
Year: 2006-2007
Location: Emlichheim Coevorden, Netherlands
Type of plant: MVA Emlichheim, NL
Installation: Construction management
Location: Emlichheim Coevorden, Netherlands
Type of plant: MVA Emlichheim, NL
Installation: Construction management
Lentjes GmbH
Year: 2007
Location: Madeira, Portugal
Type of plant: ETRSU Madeira
Installation: Warranty
Location: Madeira, Portugal
Type of plant: ETRSU Madeira
Installation: Warranty
LAB Group Stuttgart
Year: 2006
Location: Buschhaus, Germany
Type of plant: TRV Buschhaus
Installation: Construction management
Location: Buschhaus, Germany
Type of plant: TRV Buschhaus
Installation: Construction management
AE&E Lentjes Ratingen
Year: 2002-2006
Location: Allington, Great Britain
Type of plant: AVA Allington
Installation: Commissioning, loop checks, warranty services
Location: Allington, Great Britain
Type of plant: AVA Allington
Installation: Commissioning, loop checks, warranty services
LAB Group Stuttgart
Year: 2006
Location: Wels, Germany
Type of plant: WAV II Wels
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Wels, Germany
Type of plant: WAV II Wels
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Fisia Babcock Environment
Year: 2006
Location: Hameln, Germany
Type of plant: MVA Hameln
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Hameln, Germany
Type of plant: MVA Hameln
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Caliqua
Year: 2006
Location: Wels, Germany
Type of plant: WAV II Wels
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Wels, Germany
Type of plant: WAV II Wels
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Caliqua
Year: 2006
Location: Lausanne, Switzerland
Type of plant: MVA Lausanne
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Lausanne, Switzerland
Type of plant: MVA Lausanne
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
TBF + Partner GmbH
Year: 2004-2005
Location: Wels, Austria
Type of plant: WAV II Wels
Installation: Assembly manager
Location: Wels, Austria
Type of plant: WAV II Wels
Installation: Assembly manager
Martin GmbH Munich
Year: 2003-2005
Location: Amsterdam, Netherlands
Type of plant: AVI Amsterdam
Installation: Construction management, cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Amsterdam, Netherlands
Type of plant: AVI Amsterdam
Installation: Construction management, cold commissioning, hot commissioning and trial operation with commissioning shift management
LAB Group Stuttgart
Year: 2005
Location: Leuna, Germany
Type of plant: TREA Leuna
Installation: Construction management
Location: Leuna, Germany
Type of plant: TREA Leuna
Installation: Construction management
Fisia Babcock Environment
Year: 2004-2005
Location: Oberhausen, Germany
Type of plant: MVA Oberhausen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Oberhausen, Germany
Type of plant: MVA Oberhausen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
LAB Group Stuttgart
Year: 2005
Location: Rothensee – Magdeburg, Germany
Type of plant: SWM Rothensee
Installation: Project planning, planning, construction management and commissioning
Location: Rothensee – Magdeburg, Germany
Type of plant: SWM Rothensee
Installation: Project planning, planning, construction management and commissioning
Koch AG, Zürich / Schweiz
Year: 2005
Location: Bremen, Germany
Type of plant: MVA Bremen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management
Location: Bremen, Germany
Type of plant: MVA Bremen
Installation: Cold commissioning, hot commissioning and trial operation with commissioning shift management